A skill for teams planning and delivering data center facilities, from new data halls and colo deployments to cloud extensions. It covers requirements, power and cooling, physical layout, connectivity, commissioning, and handoff.
Key features
- 01Define facility requirements and site strategy
- 02Plan power chains and cooling capacity
- 03Design rack, aisle, and cable layouts
- 04Plan carrier and cloud connectivity
- 05Coordinate procurement, installation, and commissioning
- 06Prepare acceptance tests and operations handoff
Use cases
- 01Compare build, colo, and cloud extension options
- 02Estimate current and future rack and power needs
- 03Review electrical diagrams and rack layouts
- 04Create commissioning checklists and operations runbooks
Install
Copy the command and run it in a terminal.
$
npx skills add https:/ / github.com/ rade-nugroho/ agentic-enteprises-skill --skill data-center-design-execution-leadAfter installing, type/data-center-design-execution-leadin Claude Code to confirm it loaded.
Bundled files
References and scripts installed along with SKILL.md.
references/execution_commissioning.mdfacility_requirements.mdnetwork_connectivity.mdoperations_handoff.mdphysical_layout.mdpower_cooling.mdDetails
From the project READMEData Center Design Execution Lead
When to Use
- Define requirements for a new data hall, cage, or colo deployment
- Compare build vs colo vs cloud extension for a workload footprint
- Size power, cooling, and rack count for current and 3–5 year growth
- Review mechanical/electrical single-line diagrams and rack elevations
- Plan hot/cold aisle, containment, and cable pathways
- Specify network demarc, cross-connects, and latency to cloud regions
- Run design → procurement → install → commissioning → handoff
- Prepare acceptance tests and operations runbooks for facilities team
When NOT to Use
- Terraform, cloud networking, managed Kubernetes →
infrastructure-engineer - Helm, cluster add-ons, pod troubleshooting →
cluster-deployment-engineer - Application integration ADRs →
senior-system-architecture - Multi-team software program RAID →
technical-program-manager - SOC 2 control catalog without facility scope →
compliance-engineer - Physical security policy program only →
cybersecurity,information-security-engineer - Executive comms for launches →
communication-lead - Utilization, GPU supply forecast, consolidation, refresh →
data-center-compute-supply-efficiency - Multi-site roadmap, portfolio funding, steering →
data-center-portfolio-planning-execution-lead - Delivery schedule, rack-ready gates, construction RAID →
senior-data-center-capacity-delivery-manager
Related skills
| Need | Skill |
|---|---|
| Hybrid on-prem virtualization patterns | infrastructure-engineer |
| Workloads hosted in on-prem K8s | cluster-deployment-engineer |
| Large build program coordination | technical-program-manager |
| Physical/logical security controls | cybersecurity, information-security-engineer |
| Compliance evidence for facilities | compliance-engineer |
| Stakeholder and exec updates | communication-lead |
| Rollout of apps into new site | deployment-strategist |
| Compute supply and resource efficiency | data-center-compute-supply-efficiency |
| Enterprise DC portfolio planning | data-center-portfolio-planning-execution-lead |
| Capacity delivery program | senior-data-center-capacity-delivery-manager |
| On-site install, labeling, acceptance | field-services-engineer |
Core Workflows
1. Requirements and site strategy
Capture:
- Workload type (enterprise IT, HPC/GPU, edge)
- Availability target (tier intent, RTO/RPO for facility)
- Growth: racks, kW, network ports by year
- Constraints: geography, latency to users/cloud, sustainability, budget
Decide: own build, colo cage, or cloud-only with small edge.
See references/facility_requirements.md.
2. Power and cooling
- Design power chain: utility → ATS/STS → UPS → PDU → rack
- Size for peak kW/rack (air vs liquid, GPU trays)
- Cooling: CRAC/CRAH, containment, setpoints per ASHRAE class
- Target PUE and measurement points
See references/power_cooling.md.
3. Physical layout
- Rack rows, aisle width, floor load (lbs/sq ft)
- Hot/cold containment; overhead vs underfloor delivery
- Cable trays, fiber pathways, ladder rack
- Staging, spares, and restricted zones
See references/physical_layout.md.
4. Network and connectivity
- Meet-me room, carrier diversity, cross-connect model
- Core/distribution/toR switching for facility (distinct from app network design in cloud)
- Latency and bandwidth to primary cloud region for hybrid
See references/network_connectivity.md.
5. Execution and commissioning
| Phase | Deliverables |
|---|---|
| Design | BoM, drawings, capacity model sign-off |
| Procure | Long-lead gear tracked (switching, PDUs, genset) |
| Install | MEP fit-out, rack/stack, labeling standard |
| Commission | IST/FAT, red-tag clearance, integrated tests |
| Handoff | DCIM, monitoring, as-built, ops training |
See references/execution_commissioning.md.
6. Operations handoff
- DCIM asset records match labels and diagrams
- Environmental and power alarms to NOC
- Maintenance windows and vendor SLAs documented
- Runbooks: escort, smart hands, emergency power-down
See references/operations_handoff.md.
Output standards
- Capacity table: rack ID, kW design, weight, network Uplinks
- One-line diagram summary (power and cooling) with margins noted
- Commissioning checklist with pass/fail and owner
- Risks: single points of failure, lead-time items, permit dependencies
When to load references
- Site, tier, capacity →
references/facility_requirements.md - Power, UPS, cooling, PUE →
references/power_cooling.md - Racks, aisles, containment →
references/physical_layout.md - Carriers, MMR, hybrid links →
references/network_connectivity.md - Build phases and commissioning →
references/execution_commissioning.md - DCIM and ops →
references/operations_handoff.md
Comments
Markdown supported