earned-value-mgmt

earned-value-mgmt

github.com/gajetosoProductivity4343 installsUpdated 4w ago
Repository

About earned-value-mgmt

This skill applies earned value management metrics to project scope, schedule, and cost for project finance and management work. It calculates performance indices and completion forecasts, including the efficiency required for remaining work.

Key features

  1. 01Calculates CPI and SPI
  2. 02Forecasts Estimate at Completion
  3. 03Calculates Variance at Completion
  4. 04Calculates remaining-work efficiency with TCPI
  5. 05Formats a project performance dashboard

Use cases

  1. 01Check for budget overruns or schedule delays
  2. 02Forecast final cost from current performance
  3. 03Assess required efficiency for remaining work

Install

Copy the command and run it in a terminal.

$npx skills add https://github.com/gajetoso/financeskills --skill earned-value-mgmt

After installing, type/earned-value-mgmtin Claude Code to confirm it loaded.

Bundled files

References and scripts installed along with SKILL.md.

EXAMPLE.md
evals/
evals.json
evals/files/
project_status.csv
references/
forecasting-eac.md
pmi-evm.md
scripts/
calculate.py

Details

From the project README

Earned Value Management (EVM)

You are a Project Finance Manager. Your goal is to integrate project scope, schedule, and cost to provide a clear view of whether a project is on track to finish on time and on budget.

Initial Assessment

  1. The Baseline

    • Planned Value (PV): The budgeted cost of work scheduled to be done.
    • BAC: Budget at Completion.
  2. The Reality

    • Actual Cost (AC): The cost actually incurred for the work done.
    • Earned Value (EV): The budgeted cost of work actually performed.

EVM Framework

The Key Ratios
  1. Cost Performance Index (CPI): EV / AC. (Target > 1.0).
  2. Schedule Performance Index (SPI): EV / PV. (Target > 1.0).
The Forecasts
  1. Estimate at Completion (EAC): BAC / CPI. (Predicts total cost based on current performance).
  2. Variance at Completion (VAC): BAC - EAC.

Technical Project Steps

1. Percent Complete Calculation
  • Determine the objective completion of each task (e.g., 50% of the foundation is poured).
2. To-Complete Performance Index (TCPI)
  • (BAC - EV) / (BAC - AC).
  • This tells you the efficiency needed on remaining work to stay within budget.

Output Format

Project Performance Dashboard

Key Metrics

  • CPI: (e.g., 0.92 - Over Budget).
  • SPI: (e.g., 1.05 - Ahead of Schedule).

Forecasting

  • Original Budget (BAC): $1M.
  • Projected Final Cost (EAC): $1.08M.
  • Estimated Completion Date: (Based on SPI).

Corrective Actions

  • "Project is trending over budget due to higher labor rates; SPI suggests we can trade speed for cost-cutting."

Scripts

  • calculate.py: Deterministic functions for this skill's core computations. Run python3 scripts/calculate.py to self-test; import the functions instead of doing mental math.

References


Related Skills

  • budget-forecast: For setting the original project budget.
  • financial-analysis: For analyzing the impact of project overruns on company health.
  • capital-budgeting: For evaluating if the project still meets its NPV targets.