planning-and-task-breakdown

planning-and-task-breakdown

github.com/alexbrunoその他09 回インストール今日更新
リポジトリ

planning-and-task-breakdown について

`spec-driven-workflow`(`workflow/SPEC.md`、`workflow/PLAN.md`、必要に応じて `workflow/TASKS.md`)に沿って実行を計画し、複雑な作業を順序立てた検証可能なタスクに分割します。仕様を具体的な実行計画に変換する、大規模または曖昧な作業の範囲を定める、依存関係を整理する、並行可能なタスクを準備する際に使います。

インストール

コマンドをコピーしてターミナルで実行します。

$npx skills add https://github.com/alexbruno/dev-skills --skill planning-and-task-breakdown

インストール後、Claude Code で/planning-and-task-breakdownを入力して読み込まれたか確認します。

README(原文)English

プロジェクトの README より

この README の日本語訳はまだありません。以下は英語の原文です。日本語の紹介はページ上部をご覧ください。

Planning & Task Breakdown

Decompose specifications into clear execution steps (workflow/PLAN.md) and, when warranted, small verifiable tasks (workflow/TASKS.md) before writing any implementation code.

Language & Architecture Agnostic: This skill applies to any technology stack, domain, or project structure. Reason in terms of deliverables, boundaries, dependencies, and verification—never assume specific languages, frameworks, or architectural patterns.

Core Rule

Plan in read-only mode. Explore the repository, map dependencies, and write the plan before modifying any deliverable files. Do not start implementing while planning.

When to Apply

  • Translating workflow/SPEC.md into an actionable execution plan (workflow/PLAN.md).
  • Work feels too large, ambiguous, or multi-faceted to execute in a single pass.
  • Multiple independent deliverables or parallel/asynchronous agent executions are possible.
  • Skip formal breakdown for trivial, single-step edits where planning adds no value.

Planning Process

1. Ground in workflow/SPEC.md
  1. Read workflow/SPEC.md (or workflow/<change-slug>/SPEC.md for scoped initiatives).
    • If SPEC.md does not exist yet for a non-trivial change, create and align on SPEC.md first.
  2. Confirm goals, non-goals, constraints, and acceptance criteria are unambiguous. Surface open questions before committing to a plan.
2. Explore & Map Dependencies (Read-Only)
  1. Inspect the relevant areas of the repository (preferring indexed context if codebase-indexing is active).
  2. Identify affected components, shared boundaries, and external constraints.
  3. Map the dependency graph: determine what blocks what, which steps must run sequentially, and which units are truly independent.
3. Author workflow/PLAN.md

Create or update workflow/PLAN.md (initializing workflow/ if missing):

  • Reference SPEC.md requirements rather than duplicating them.
  • Order steps logically—tackle high-risk or high-uncertainty unknowns early.
  • Define a concrete Verification Strategy (automated checks, validations, or manual verification) for each step and for the overall change.
  • Note risks and rollback considerations.
4. Shard into workflow/TASKS.md (Conditional)

Create workflow/TASKS.md only when at least one spec-driven-workflow trigger applies:

  1. PLAN.md is too large or comprehensive to execute cleanly in a single pass.
  2. PLAN.md spans two or more distinct scopes, task types (feature, bugfix, refactor, docs), or independent deliverables that benefit from separate tracking.
  3. Work can be split into independent units executed in parallel or asynchronously by different agents or contributors.

When creating TASKS.md, ensure every task has:

  • Unique ID & Type (e.g., T1, feature | bugfix | refactor | docs | chore).
  • Explicit Dependencies: Clearly state blocking task IDs (or None).
  • Disjoint Scope: Assign non-overlapping files or modules to parallel tasks to prevent merge conflicts.
  • Objective Done Criteria: Concrete, verifiable conditions that prove the task is complete.

Quality Checklist

Before handing off PLAN.md (and TASKS.md) for execution:

  1. Every requirement and acceptance criterion in workflow/SPEC.md is covered by at least one step or task.
  2. No circular dependencies exist, and parallel tasks have non-overlapping scopes.
  3. Every step/task is small enough to implement and verify in a single focused pass.
  4. No implementation code has been written prematurely during the planning phase.